The Use of Project Time Management Processes and the Schedule Performance of Construction Projects in Mexico

Table 9

Mean SV values obtained for different periods of time (variance in number of weeks).

ProjectsPerformance at project completionMean SPI values
4th week8th week12th weekLast week

1Delayed−1.59−1.86−1.85−1.73
2On time0.730.900.570.57
3Delayed−0.23−0.23−0.31−0.55
4Delayed−2.04−2.06−1.53−1.34
5Delayed−0.31−0.04−0.02−0.90
6On time3.062.712.381.90
7On time−0.22−0.78−0.56−0.47
8On time0.04−0.18−0.11−0.03
9Delayed−0.67−0.74−0.45−0.61
10Delayed−1.240.250.61−0.82
11On time2.592.351.811.31
12Delayed−1.74−2.56−2.15−1.87
13On time−1.09−2.13−2.43−2.10
14On time−0.86−1.06−1.04−0.96

Projects that were granted an extension of time.