Critical Factors Inhibiting Performance of Small- and Medium-Scale Contractors in Sub-Saharan Region: A Case for Malawi
Table 1
Performance classification of small- to medium-scale contracts executed between 2007/08 and 2010/11 FYs.
|
Scale | Successful | Fair | Unsuccessful | Completed ahead of time or on time | Ex gratia extension of time granted for project to be completed | Liquidated damages applied, or contract terminated or closed uncompleted |
| Small | 571 | 309 | 205 | Medium | 143 | 45 | 54 | Total | 714 | 354 | 259 |
| Percentage against total contracts executed by SMCs | 53.8% | 26.7% | 19.5% |
|
|