Research Article

Deviations between Contract Sums and Final Accounts: The Case of Capital Projects in Ghana

Table 3

Factors influencing the deviations between contract sums and the final accounts for capital projects in Ghana.

S. numberFactorsContractorConsultantClientsCombined
MeanRankMeanRankMeanRankMeanRank

1Changes in design4.3954.5634.4454.464
2Changes in the scope of work4.4834.4654.4744.473
3Price fluctuation4.5314.6714.7114.641
4Fluctuation in the market demand4.4444.3084.5134.425
5Late material delivery4.5124.6124.5924.572
6Bureaucracy in tendering method1.86391.67391.50391.6839
7Economic stability1.25401.18401.23401.2240

Source: field survey, 2014.