Deviations between Contract Sums and Final Accounts: The Case of Capital Projects in Ghana

Table 5

Significant test of the factors that cause the deviation between the contract sum and final account for capital projects in Ghana.

NumberFactorsChi-sq.dfAsym. sig. Ranks

1Increase in interest rate20.36430.000Sig.
2Obtaining permit20.72730.000Sig.
3Changes in design32.18230.000Sig.
4Discrepancies between design specifications and code20.54530.000Sig.
5Inadequate programme scheduling22.68220.000Sig.
6Contractors poor management ability25.27330.000Sig.
7Defects in design22.36430.000Sig.
8Underestimation58.72730.000Sig.
9Overestimation43.04540.000Sig.
10Delay in resolving disputes3140.000Sig.
11Feasibility of construction methods11.81830.000Sig.
12Price fluctuation30.72730.000Sig.
13Shortage of materials on site26.45540.000Sig.
14Late material delivery19.09130.000Sig.
15Mode of financing38.77320.000Sig.
16Default of contractor27.81830.000Sig.
17Fluctuation in the market demand13.54540.001Sig.
18Bureaucracy in tendering method13.27320.001Sig.
19Unexpected site conditions16.68240.002Sig.
20Changes in the scope of work15.54540.004Sig.
21Insurance cost15.54540.004Sig.
22Damage by flood12.54530.006Sig
23Government policies9.86420.007Sig
24Use of inappropriate plant13.68220.01Sig
25Bad weather19.63640.01Sig.
26Accident during construction9.63630.022Sig.

Significant at 0.05 significance level.