Deviations between Contract Sums and Final Accounts: The Case of Capital Projects in Ghana
Table 5
Significant test of the factors that cause the deviation between the contract sum and final account for capital projects in Ghana.
| Number | Factors | Chi-sq. | df | Asym. sig. | Ranks |
| 1 | Increase in interest rate | 20.364 | 3 | 0.000 | Sig. | 2 | Obtaining permit | 20.727 | 3 | 0.000 | Sig. | 3 | Changes in design | 32.182 | 3 | 0.000 | Sig. | 4 | Discrepancies between design specifications and code | 20.545 | 3 | 0.000 | Sig. | 5 | Inadequate programme scheduling | 22.682 | 2 | 0.000 | Sig. | 6 | Contractors poor management ability | 25.273 | 3 | 0.000 | Sig. | 7 | Defects in design | 22.364 | 3 | 0.000 | Sig. | 8 | Underestimation | 58.727 | 3 | 0.000 | Sig. | 9 | Overestimation | 43.045 | 4 | 0.000 | Sig. | 10 | Delay in resolving disputes | 31 | 4 | 0.000 | Sig. | 11 | Feasibility of construction methods | 11.818 | 3 | 0.000 | Sig. | 12 | Price fluctuation | 30.727 | 3 | 0.000 | Sig. | 13 | Shortage of materials on site | 26.455 | 4 | 0.000 | Sig. | 14 | Late material delivery | 19.091 | 3 | 0.000 | Sig. | 15 | Mode of financing | 38.773 | 2 | 0.000 | Sig. | 16 | Default of contractor | 27.818 | 3 | 0.000 | Sig. | 17 | Fluctuation in the market demand | 13.545 | 4 | 0.001 | Sig. | 18 | Bureaucracy in tendering method | 13.273 | 2 | 0.001 | Sig. | 19 | Unexpected site conditions | 16.682 | 4 | 0.002 | Sig. | 20 | Changes in the scope of work | 15.545 | 4 | 0.004 | Sig. | 21 | Insurance cost | 15.545 | 4 | 0.004 | Sig. | 22 | Damage by flood | 12.545 | 3 | 0.006 | Sig | 23 | Government policies | 9.864 | 2 | 0.007 | Sig | 24 | Use of inappropriate plant | 13.682 | 2 | 0.01 | Sig | 25 | Bad weather | 19.636 | 4 | 0.01 | Sig. | 26 | Accident during construction | 9.636 | 3 | 0.022 | Sig. |
|
|
Significant at 0.05 significance level.
|