Risk Level Assessment in Construction Projects Using the Schedule Performance Index

1Federal University of Alagoas, Maceió, AL, Brazil
2Federal University of Santa Catarina, Florianópolis, SC, Brazil

Received 7 June 2016; Accepted 5 October 2016

Academic Editor: Edwin H. W. Chan

Copyright © 2016 Roberto Barbosa dos Santos and Antônio Edésio Jungles. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

Linked References

  1. J. Bourn, Modernising Construction, National Audit Office, London, UK, 2001.
  2. J. Bourn, PFI: Construction Performance [Internet], HC. UK: National Audit Office, 2003, http://www.nao.org.uk/wp-content/uploads/2003/02/0203371.pdf.
  3. E. Pereira, C. D. N. Mutti, and A. Jungles, “Prevision of delay in Brazilian residential unit construction contracts,” Journal of Civil Engineering and Architecture, vol. 8, no. 1, pp. 100–106, 2014. View at Google Scholar
  4. H. Abdul-Rahman, C. Wang, and N. H. Ariffin, “Identification of risks pertaining to abandoned housing projects in Malaysia,” Journal of Construction Engineering, vol. 2015, Article ID 524717, 12 pages, 2015. View at Publisher · View at Google Scholar
  5. K. Yeo, “Risks, classification of estimates, and contingency management,” Journal of Management in Engineering, vol. 6, no. 4, pp. 458–470, 1990. View at Publisher · View at Google Scholar
  6. K. Offei-Nyako, L. C. O. Tham, M. Bediako, C. D. Adobor, and R. O. Asamoah, “Deviations between contract sums and final accounts: the case of capital projects in Ghana,” Journal of Construction Engineering, vol. 2016, Article ID 2814126, 8 pages, 2016. View at Publisher · View at Google Scholar
  7. P. P. Shrestha, L. A. Burns, and D. R. Shields, “Magnitude of construction cost and schedule overruns in public work projects,” Journal of Construction Engineering, vol. 2013, Article ID 935978, 9 pages, 2013. View at Publisher · View at Google Scholar
  8. PMBoK, A Guide to the Project Management Body of Knowledge, Project Management Institute, Pennsylvania, Pa, USA, 2013.
  9. R. Chapman, “The controlling influences on effective risk identification and assessment for construction design management,” International Journal of Project Management, vol. 19, no. 3, pp. 147–160, 2001. View at Publisher · View at Google Scholar
  10. G. A. Barraza and R. A. Bueno, “Probabilistic control of project performance using control limit curves,” Journal of Construction Engineering and Management, vol. 133, no. 12, pp. 957–965, 2007. View at Publisher · View at Google Scholar
  11. G. A. Barraza, W. E. Back, and F. Mata, “Probabilistic monitoring of project performance using SS-curves,” Journal of Construction Engineering and Management, vol. 126, no. 2, pp. 142–148, 2000. View at Publisher · View at Google Scholar · View at Scopus
  12. S. Hwang, “Dynamic regression models for prediction of construction costs,” Journal of Construction Engineering and Management, vol. 135, no. 5, pp. 360–367, 2009. View at Publisher · View at Google Scholar
  13. S. M. Trost and G. D. Oberlender, “Predicting accuracy of early cost estimates using factor analysis and multivariate regression,” Journal of Construction Engineering and Management, vol. 129, no. 2, pp. 198–204, 2003. View at Publisher · View at Google Scholar
  14. P. Gardoni, K. F. Reinschmidt, and R. Kumar, “A probabilistic framework for bayesian adaptive forecasting of project progress,” Computer-Aided Civil and Infrastructure Engineering, vol. 22, no. 3, pp. 182–196, 2007. View at Publisher · View at Google Scholar
  15. B.-C. Kim and K. F. Reinschmidt, “Probabilistic forecasting of project duration using Kalman filter and the earned value method,” Journal of Construction Engineering and Management, vol. 136, no. 8, pp. 834–843, 2010. View at Publisher · View at Google Scholar
  16. H.-H. Choi and S. Mahadevan, “Construction project risk assessment using existing database and project-specific information,” Journal of Construction Engineering and Management, vol. 134, no. 11, pp. 894–903, 2008. View at Publisher · View at Google Scholar · View at Scopus
  17. H. Abdul-Rahman, C. Wang, and F. S. Mohamad, “Implementation of risk management in malaysian construction industry: case studies,” Journal of Construction Engineering, vol. 2015, Article ID 192742, 6 pages, 2015. View at Publisher · View at Google Scholar
  18. A. Sohrabinejad and M. Rahimi, “Risk determination, prioritization, and classifying in construction project case study: gharb tehran commercial-administrative complex,” Journal of Construction Engineering, vol. 2015, Article ID 203468, 10 pages, 2015. View at Publisher · View at Google Scholar
  19. M. R. Hallowell, K. R. Molenaar, and B. R. Fortunato III, “Enterprise risk management strategies for state departments of transportation,” Journal of Management in Engineering, vol. 29, no. 2, pp. 114–121, 2013. View at Publisher · View at Google Scholar
  20. E. M. Goldratt, Corrente Crítica, Nobel, São Paulo, Brazil, 1998.
  21. PMI PMI-, Um Guia do Conjunto de Conhecimentos em Gerenciamento de Projetos, 3a, EUA: PMI, 2013.
  22. M. M. S. Bernardes and C. T. Formoso, “Contributions to the evaluation of production planning and pontrol systems in building companies,” in Proceedings of the Annual Conference of the International Group for Lean Construction, pp. 1–11, Gramado, Brazil, August 2002.
  23. K. Fung, Os Números Governam sua vida: A Influência Velada das Probabilidades e da Estatística em Tudo o que Você Faz, DVS Editora, São Paulo, Brazil, 2011.
  24. B.-C. Kim, Forecasting Project Progress and Early Warning of Project Overruns with Probabilistic Methods, Texas A&M University, 2007.