Risk Level Assessment in Construction Projects Using the Schedule Performance Index

Table 3

Statistics for the SPI.

GroupStatisticsSPI3SPI6SPI9SPI12

All projects19191919
Average0.81130.79850.75440.7078
Variance0.33920.33260.29570.3011
Coefficient of variation41.8131%41.6509%39.1985%42.5332%

Delayed15151515
Average0.75430.73040.67630.6139
Variance0.36170.29580.27740.2505
Coefficient of variation47.9535%40.4958%41.0208%40.8064%

Without delay4444
Average1.02501.05381.04741.0602
Variance0.05230.38120.14370.2032
Coefficient of variation5.1015%36.1692%13.7161%19.1666%