Risk Level Assessment in Construction Projects Using the Schedule Performance Index
| | Source | SS | Df | MS | | Prob > |
| SPI3 | Groups | 0.23144 | 1 | 0.23144 | 2.14 | 0.1619 | Error | 1.83985 | 17 | 0.10823 | | | Total | 2.07129 | 18 | | | |
| SPI6 | Groups | 0.26428 | 1 | 0.26428 | 2.85 | 0.1123 | Error | 1.39334 | 15 | 0.09289 | | | Total | 1.65763 | 16 | | | |
| SPI9 | Groups | 0.31617 | 1 | 0.31617 | 7.72 | 0.0167 | Error | 0.49148 | 12 | 0.04096 | | | Total | 0.80766 | 13 | | | |
| SPI12 | Groups | 0.37138 | 1 | 0.37138 | 6.1 | 0.0355 | Error | 0.54768 | 9 | 0.06085 | | | Total | 0.91906 | 10 | | | |
|
|