Maintainability Analysis of Underground Mining Equipment Using Genetic Algorithms: Case Studies with an LHD Vehicle

Table 6

Delay data composition for the period from January to June 2006.

Type of delayJanuary–June 2006May–October 2006
Time Frequency Percent age (%) Time Frequency Percent age (%)

AV 28.3 9 2.17 102 21 10.48
ME 74 10 5.69 44.7 7 4.59
MH 294.1 32 22.60 279.6 27 28.73
MI 4 1 0.31 4 1 0.41
MM 720.9 74 55.40 480.9 46 49.41
MP 172 16 13.22 62 7 6.37
OW 8 1 0.61 0 0 0.00

Total 1301.3 143 100 973.2 109 100