Worldwide Status of CCUS Technologies and Their Development and Challenges in China

Table 3

Main engineering CCUS projects in China.

ProjectsLocationScale tons/yrCO2 capture methodStorage/utilizationStatus

() CO2-EOR project by Daqing oilfieldsYushulin, HailaerEOROperation
() CO2-EOR project by Jilin oilfieldSongyuan0.28 millionLiquefaction of FCC flue gasEOROperation
(2-1) Second stage of EOR project in Jilin oilfieldSongyuanPlanned for 0.5 millionPrecombustion from the separation of natural gas productionEOROperation
() CO2-EOR project by Shengli oilfieldDongying40,000PostcombustionEOROperation
() EOR project by Zhongyuan oilfieldPuyang100,000Post-combustionEOROperation
() EOR project by Yanchang oilfieldYanchang400,000Coal liquefaction plantEOROperation
() First stage of Huaneng greengen IGCC in TianjinTianjinPre-combustionPlaned for EOROperation
() CO2-ECBM by China United Coalbed Methane Ltd.Jincheng40/dayPurchase of CO2ECBMCompleted
() Full chain CCS project by Shenhua GroupOrdos100,000Coal liquefaction plantSaline formationCompleted
() Pilot project of IGCC clean energy in LianyungangLianyungang1000,000Pre-combustionPlaned in saline formationPreparation
() 35 MWt oxy-fuel combustion in Zhongyan Yingcheng of HubeiYingcheng100,000Oxy-fuel combustionSequestration in the salt rockPreparation
() CO2 capture and storage pilot project by China Resources PowerDongguan1 millionPre-/post-combustion from power station and oil refineryPlaned for EOR or saline formationPrefeasibility study
() Coal-to-liquids project in Ningxia by Shenhua GroupNingxia2 millionPre-combustion from the coal-to-liquids processUndefinedOpportunity study
() Third stage of Huaneng greengen IGCC in TianjinTianjin2 millionPre-combustion from the power stationPlaned for EOR saline formationNot start
() Second stage of coal-to-liquids project by Shenhua GroupOrdos1 millionPre-combustion from the coal-to-liquids processSaline formationPrefeasibility study
() CCS project by Sinopec Qilu PetrochemicalDongying0.5 millionPre-combustion from oil refineryEORPreliminary design
() CCS project of Shengli power station by Datang GroupDongying1 millionPost-combustion from the power stationEORPrefeasibility study
() CO2 capture and EOR in coal chemical industry by Yangchang Petroleum Co. Ltd.Yanchang5,0000Pre-combustion from coal chemical industryEOROperation
(17-1) Second stage of CO2 capture and storage project by Yanchang GroupYanchang1 millionPre-combustion from coal chemical industryEORNot start
() CO2 capture and storage pilot project in Daqing oilfield by Datang GroupDaqing1 millionOxy-fuel combustion from the power stationPlaned for EOR + saline formationPrefeasibility study
Coal-to-gas project by CNOOC DatongDatong1 millionPre-combustion from coal-to-gas processPlaned for EOR + saline formationPrefeasibility study
Coal-to-gas project by CNOOC OrdosOrdos1 millionPre-combustion from coal-to-gas processPlaned for EOR + saline formationPre-feasibility study
Coal-to-olefin Ordos project by CPIC and TOTALOrdos1 millionPre-combustion from coal-to-olefin processPlaned for EOR + saline formationPrefeasibility study
CCUS project by Shanxi international energy groupShanxi2 millionOxy-fuel combustion from the power stationUndefinedPrefeasibility study

Industrial conversion of the captured CO2, not for underground geological sequestration
() Pilot project of CO2 sequestration by microalgae of Xin’ao GroupDalate qi320,000Flue gas of the coal chemistry factoryMicrobe sequestrationConstruction
() SNG project in Qinghua of XinjiangYili in XinjiangPre-combustionMicrobe sequestrationOperation
() Geothermal power station in Gaobeidian of Beijing by HuanengBeijing3000Post-combustionFood and industry useOperation
() Shidongkou project in Shanghai by HuanengShanghai120,000Post-combustionFood and industry useOperation
() Shuanghuai power plant projectChongqing10,000Post-combustionN/AOperation
() CO2 project in HainanDongfang2100Separation from natural gasBiodegradable plasticsOperation
() CO2 project in JiangsuTaixing8000Alcohol factoryChemical materialOperation
() CO2 pilot project in TianjinTianjin20,000Post-combustionFoodPreparation

Note. Projects marked with threaten cancellation in the near future for unknown reasons.