Research Article

Planning of Hybrid Micro-Hydro and Solar Photovoltaic Systems for Rural Areas of Central Java, Indonesia

Table 3

Total capital costs for various configurations of the hybrid solar photovoltaic and micro-hydro systems.

NumberConfiguration of hybrid power plantTotal capital cost (US $)

1Grid + micro-hydro1,132,426
2Grid + micro-hydro + PV 10 kW1,265,076
3Grid + micro-hydro + PV 20 kW1,286,371
4Grid + micro-hydro + PV 30 kW1,294,443
5Grid + micro-hydro + PV 40 kW1,309,537