Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms
Table 4
PNS properties of control account (CA).
| Property (P-) | Value | Code | Classifications |
| PL: project life cycle | PL1: planning PL2: engineering PL3: procurement PL4: construction PL5: start-up and operation PL6: fuel PL7: project management | PRE ENG PRO CON OSS FUL PMO | EVMS standards |
| PU: facility unit | PU0: shared PU1: unit 1 PU2: unit 2 PU9: general requirements | 0 1 2 9 | Company general standards |
| PD: deliverable type | PDP: planning documents PDD: drawings PDE: specifications PDR: report PDC: combined PDL: as-built  PDN: NSSS PDT: turbine generator PDB: BOP PDO: construction PDA: start-up assistance PDS: start-up PDM: operation and maintenance PDU: training PDI: ICT PDF: fuel PDZ: project management | P D E R C L N T B O A S M U I F Z | EVMS standards |
| PP: physical breakdown | PP1: building (BLDG) PP2: physical breakdown structure (PBS) | 3 digits 3 digits | Company general standards |
| PF: functional breakdown | PF1: functional breakdown structure (FBS) PF2: construction packages (CP) PF3: organization breakdown structure (OBS) | 4 digits 4 digits 1 digit | Company general standards |
|
|