Research Article

Integrated Cost and Schedule Control Systems for Nuclear Power Plant Construction: Leveraging Strategic Advantages to Owners and EPC Firms

Table 4

PNS properties of control account (CA).

Property (P-)ValueCodeClassifications

PL: project life cyclePL1: planning
PL2: engineering
PL3: procurement
PL4: construction
PL5: start-up and operation
PL6: fuel
PL7: project management
PRE
ENG
PRO
CON
OSS
FUL
PMO
EVMS
standards

PU: facility unitPU0: shared
PU1: unit 1
PU2: unit 2
PU9: general requirements
0
1
2
9
Company
general
standards

PD: deliverable typePDP: planning documents
PDD: drawings
PDE: specifications
PDR: report
PDC: combined
PDL: as-built 
PDN: NSSS
PDT: turbine generator
PDB: BOP
PDO: construction
PDA: start-up assistance
PDS: start-up
PDM: operation and maintenance
PDU: training
PDI: ICT
PDF: fuel
PDZ: project management
P
D
E
R
C
L
N
T
B
O
A
S
M
U
I
F
Z
EVMS
standards

PP: physical breakdownPP1: building (BLDG)
PP2: physical breakdown structure (PBS)
3 digits
3 digits
Company
general
standards

PF: functional breakdownPF1: functional breakdown structure (FBS)
PF2: construction packages (CP)
PF3: organization breakdown structure (OBS)
4 digits
4 digits
1 digit
Company
general
standards