The Influence of an Information Environment on Construction Organization's Culture: A Case Study

Table 1

Weekly report and director’s report.
(a) Individual project performance from weekly report

Unforeseen (UF) & Owner (0) Risk
# UF Risks affecting budget/schedule0
Days delayed (Calendar)0
Additional costs0
# 0. Risk affecting budget/schedule1
Days delayed (Calendar)0
Additional costs$2.000.00

Above risks include potential and resolved

Contractor risks
# of Unaddressed/Overdue Risks1
# Unrated risks0
# Risks affecting budget/schedule2
Risks to schedule (calendar days)15
Risk to cost$1.000.00
Contractor satisfaction rating10

Above risks include potential and resolved

Overall current status
Days delayed (calendar days)5
% Delayed0.8%
Contractor % delayed0.8%
Additional costs$2.000.00
% Over award9.2%
Contractor % over award0%
Project satisfaction rating10
Risk number1.16
Above schedule and budget additions include only resolved risks

(b) Overall organization performance

Division overview25/9/2009

Original projects budget$585 999 296.63
Current estimated cost$613 872 042.82
Estimated cost over budget$27 872 746.19

Project overview

Total number of projects194
% projects on time43%
Number of jobs delayed111
% projects on budget54%
Number of jobs over awarded budget16
Number of projects missing owner ratings0

Average project

Project schedule length in days
Project budget $3 020 614.93
% over awarded budget4.76%
% over budget due to owner3.42%
% over budget due to contractor0.03%
% over budget due to unforeseen1.31%
Average length of project529
% Delayed24.07%
% Delayed due to owner17.21%
% Delayed due to contractor1.89%
% Delayed due to unforeseen4.97%
Number of risks2.00
Number owner generated risks1.36
Number of overdue risks0.52
Owner rating9.36
Risk number2.86

(c) Risk ranking in projects

Top 10 risk ranking projects 9/25/2009
NumberProjectRisk number

1Addition to Third Floor Womans Health Care Suite42.63
2Replace Hot Water Converters28.98
3Construct Rollup Connections for Boilers & Chillers28.09
4Security Repairs18.22
5Misc. Medical Repair Projects '0813.10
6Rep, Reconf for TBI Program12.73
7Bathroom Conversions, Bldg 920012.66
8Renew Health Clinic, Building 99011.01
9Repair AHU Number 2 and Number 310.73
10Renew Smith Dental Clinic8.04

(d) Comparing vendor performance

Contractor overviewContractor AContractor BContractor C

Total awarded budget$1 202 511$474 170$4 015 198
Current cost$4 907 721$487 924$4 357 671
Over budget$3 705 210$13 754$342 473

Project overview

Total number of projects111
% Projects on time0%0%0%
Number of Jobs delayed111
% Projects on budget0%0%0%
Number of Jobs over awarded budget111

Average project

Number of Risks per job3.003.005.00
Owner generated risks0.003.005.00
Number of overdue risks101
% Over awarded budget308.12%2.90%8.53%
% over budget due to owner0.00%2.90%8.53%
% over budget due to contractor0.00%0.00%0.00%
% over budget due to unforseen308.12%0.00%0.00%
Number of Days delayed60199183
Number of days delayed due to owner099183
Number days delayed due to contractor000
Number days delayed due to unforseen60100
Owner rating10.006.716.63
Risk number13.106.166.09