Optimizing Construction Project Labor Utilization Using Differential Evolution: A Comparative Study of Mutation Strategies

Algorithm 1

CPM scheduling.
Begin Algorithm
Set Precedence Relationship, Required Work Hour, Lower and Upper Boundaries of Crewsize
// activity information
SetCrewsize // crew information of each activity
CalculateDuration // durations of activities is computed by (2)
For : ActNum // Performing forward CPM calculation
   // ActNum = number of activities
   Calculate ES() // Early start of activity
        EF() // Early finish of activity
End For
LF(ActNum) = EF(ActNum)
LS(ActNum) = LF(ActNum) − Duration(ActNum)
= ActNum − 1
While // Performing backward CPM calculation
   Calculate LF() // Late finish of activity
        LS() // Late start of activity
End While
Return ES, LS, EF, LF
End Algorithm