Research Article

Optimizing Construction Project Labor Utilization Using Differential Evolution: A Comparative Study of Mutation Strategies

Table 1

Project information.

Activity numberActivity relationshipRequired working hour (hour)

1ā€‰100
21FS220
31FS, 2SS380
41FS210
52FS, 3FS520
62FS, 4FS220
74FS, 6SS370
85FS, 7FS380
95FS, 6FS, and 8SS320
107FS630
118FS, 9FS, and 10FS100