Optimizing Construction Project Labor Utilization Using Differential Evolution: A Comparative Study of Mutation Strategies

Table 2

Example of activity duration calculation.

Activity numberRequired working hour (hour)Crew size (person)Calculated duration (shift)Rounded duration (shift)

110052.5 = 100/(5 8)3 = ceil(2.5)
222055.56
3380104.85
421055.36
5520513.013
622055.56
7370104.65
8380104.85
932058.08
10630107.98
1110071.82

Note: each shift lasts 8 hours.