Optimal Analysis of Tunnel Construction Methods through Cross Passage from Subway Shaft
Table 2
Cross passage support parameters.
| Item | Main materials and specifications | Structure size |
| Support | Big pipe shed | Φ1086 | Length: 10 m; ring spacing: 0.5 m | Leading conduit | Φ423.5, length = 2 m and 3.5 m, steel bar | Ring spacing 0.3 m | Vertical clearance: 1.5 m | Grid steel frame | C25, C14 steel bar | Vertical clearance: 0.5 m | Mesh reinforcement | Φ8 150150 m grid | Surrounded by laying, double | Vertical reinforcement | C22 steel bar | Ring spacing: 1.0 m, double | Shotcrete | C25 early strength concrete | Thickness: 0.3 m | Secondary lining | C35 waterproof reinforced concrete seepage resistance grade p10 | Thickness: 0.6 m |
|
|