Research Article

Pavement Manager at Risk in Construction of Hot Mix Asphalt

Table 6

Annual profit/loss per SY using chip seal treatment.

Number of clientsChip seal
Cost of service ($/yr)Total ($)Annual cost per 700 K SF property ($)Annual cost per SY ($)Profit/loss-charging $3/SY/yrProfit/loss-charging $3.5/SY/yr
GoodFair

1$173,701.11$155,363.33$170,550.61$329,064.44$4.23−$95,731.11−$56,842.22
2$255,912.22$271,516.67$210,401.23$527,428.89$3.39−$60,762.22$17,015.56
3$338,123.33$387,670.00$250,251.84$725,793.33$3.11−$25,793.33$90,873.33
4$420,334.44$503,823.33$290,102.45$924,157.78$2.97$9,175.56$164,731.11
5$502,545.56$619,976.67$329,953.07$1,122,522.22$2.89$44,144.44$238,588.89
6$584,756.67$736,130.00$369,803.68$1,320,886.67$2.83$79,113.33$312,446.67
7$666,967.78$852,283.33$409,654.29$1,519,251.11$2.79$114,082.22$386,304.44
8$749,178.89$968,436.67$449,504.91$1,717,615.56$2.76$149,051.11$460,162.22
9$831,390.00$1,084,590.00$489,355.52$1,915,980.00$2.74$184,020.00$534,020.00
10$913,601.11$1,200,743.33$529,206.13$2,114,344.44$2.72$218,988.89$607,877.78