Research Article

Grouting Reinforcement of Large Building Foundation over Old Gob Areas: A Case Study in Huaibei Mining Area, China

Table 5

Parameters of grouting boreholes.

Drilling no.Grouting timeGrouting amountReason for stopping grouting
StartingEndingCement (t)Fly ash (t)

Z3Jan. 14Jan. 29607.42635.2Emitting of slurry at ground
Z6Jan. 14Jan. 1534.0175.7Emitting of slurry at ground
Z7Jan. 15Feb. 201068.54216.3Emitting of slurry at ground
Z5Jan. 18Jan. 26385.41873.9Emitting of slurry at ground
Z14Feb. 6Feb. 21499.82518.1Reaching grouting pressure
Z12Feb. 18Feb. 1919.287.8Emitting of slurry at ground
Z17Feb. 21Mar. 27829.63854.4Emitting of slurry at ground
Z13Feb. 27Mar. 8139.0778.8Reaching grouting pressure
Z16Mar. 8Mar. 27190.61111.0ā€”
Z4Mar. 10Mar. 27396.32582.4Emitting of slurry at ground
Z8Mar. 22Mar. 27105.5979.2ā€”