Grouting Reinforcement of Large Building Foundation over Old Gob Areas: A Case Study in Huaibei Mining Area, China

Table 6

Characteristics of the boreholes before and after grouting.

TimeBoreholeLeakage observationDrill fellingWind inhalation

Before groutingK399.5 m to end all lost; leakage more than 15 m3/hNoYes
K6101.5 m to end all lost; leakage more than 15 m3/hNoYes
K789.9 m to end all lost; leakage more than 15 m3/hYesYes

After groutingJ1No leakingNoNo
J289.9 m to end a little lost; leakage only 0.54 m3/hNoNo
J4No leakingNoNo