Bridge Responses Induced by Adjacent Subway Station Construction Using Shallow Tunneling Method

Table 2

Construction timeline.

Construction stageStart date–end date

Nos. 1 and 2 drift cross bridge2010.10.17–2010.11.20
Nos. 3 and 4 drift cross bridge2010.11.17–2010.12.20
Construction suspended2010.12.21–2011.7.3
Jacking for the first time2011.7.4
Jacking for the second time2011.7.17
No. 5 drift cross bridge2011.7.18–2011.8.9
Arch construction2011.8.9–2011.9.14
Station concourse completion2011.9.10–2011.11.21
Station platform completion2011.11.23–2012.1.6