Public-Private Partnerships in the Electric Vehicle Charging Infrastructure in China: An Illustrative Case Study

Table 2

Risk allocation in the Anqing project.

Risk categoryGovernmentSPV

Design/construction risk
Planning and site selection risk
Land delivery and coordination risk
Design faults
Engineering technical faults
Labor and equipment acquisition
Expansion of power supply capacity
Construction preparation
General engineering variation
Cost overruns of construction and procurement
Completion risk
Site safety, environmental protection
Operation risk
Facilities’ technical defects
Commissioning test
Facilities and equipment failure
Cost overruns of operation and maintenance
Quality of service do not reach the standard
Grid load regulation
Operator default and early termination
Overhaul and asset replacement
Safety management in operation period
Environmental protection in operation period
Financial risk
Financing failure
High financing costs
Interest rate change
Foreign exchange risk
Debt risk/liquidity risk
SPV bankruptcy
Revenue risk
Change of electric car ownership/charging infrastructure utilization ratio
Government pricing changes, such as service fees
Changes in other revenue
Inflation
Legal risk
Contract document conflict
Third party default
Government behavior risk
Government default and early termination
Expropriation and nationalization
Approval delay
Special engineering variation
Tax variation
Industry standard variation
Technology variation
Other risk
Force majeure