Research Article

Key Success Indicators for PPP Projects: Evidence from Hong Kong

Table 2

Demographic information of the respondents.

Variable

Role undertaken in a Public-Private Partnership project
Public partner1418.18
Private partner5166.23
Others810.39
Unknown45.20

Public-Private Partnership project type
Hospital1215.58
Transportation2735.06
Water and sanitary22.60
Power and energy45.20
Housing1722.08
Education45.20
Defence and military22.60
Others911.68

Public-Private Partnership procurement approach adopted
Build-own-operate-transfer (BOOT)11.30
Design-build-finance-operate (DBFO)3038.96
Build-transfer-operate (BTO)79.09
Build-operate-transfer (BOT)1316.88
Build-own-operate (BOO)45.20
Build-lease-transfer (BLT)33.90
Others1215.58
Unknown79.09

Note. is the number of effective replied questionnaires; is the percentage of effective replied questionnaires.