Research Article

Resource Unconstrained and Constrained Project Scheduling Problems and Practices in a Multiproject Environment

Table 4

Kruskal–Wallis test for checking the differences between client-side and contractor-side.

ResultSummary
Variableχ2 (1, )

Significant difference exists1. Division and assignment of resources/resource allocation5.108,
3. Management support4.303,

Significant difference does not exists2. Organizational culture3.565,
4. Prioritization/project selection1.573,
5. Real-time monitoring and proactive decision making1.425,
6. Capacity0.065,
7. Complexity0.003,
8. Conflict3.495,
9. Commitment0.499,
10. Context0.051,
11. Communication0.379,
12. Coordination0.674,
13. Volatile economic environment1.107,
14. Dynamic nature0.987,
15. Duration and resources (cascade effect)0.007,
16. Competencies of project manager0.039,
17. Project manager assignment0.911,
18. Project management processes (information sharing)0.057,