Calculation results of the difference in scales between the predicted cavity and the identified cavity according to the soil depth.
| Analyzed cavities | Soil depth (m) | Identified cavity (m) | Difference of predicted and identified values (m) | Cidentified/Cpredicted (%) | Longitudinal section | Cross section | Longitudinal section | Cross section | Longitudinal section | Cross section |
| Cavity 1 | 0.11 | 1.00 | 0.90 | 0.30 | 0.30 | 76.9 | 75.0 | Cavity 2 | 0.24 | 0.50 | 0.40 | 0.35 | 0.40 | 58.8 | 50.0 | Cavity 3 | 0.27 | 1.50 | 1.20 | 0.00 | 0.00 | 100.0 | 100.0 | Cavity 4 | 0.30 | 1.60 | 0.50 | 0.00 | 0.30 | 100.0 | 62.5 | Cavity 5 | 0.35 | 1.00 | 0.50 | 0.30 | 0.10 | 76.9 | 83.3 | Cavity 6 | 0.36 | 1.60 | 2.10 | 0.10 | 0.60 | 94.1 | 77.8 | Cavity 7 | 0.40 | 1.20 | 0.65 | 0.20 | 0.15 | 85.7 | 81.3 | Cavity 8 | 0.44 | 0.70 | 1.40 | 0.60 | 0.20 | 53.8 | 87.5 | Cavity 9 | 0.46 | 1.80 | 0.40 | 0.20 | 0.40 | 90.0 | 50.0 | Cavity 10 | 0.51 | 1.00 | 0.95 | 0.40 | 0.25 | 71.4 | 79.2 |
|
|