Integration of BIM and Energy Consumption Modelling for Manufacturing Prefabricated Components: A Case Study in China

Table 10

Energy consumption data of each equipment for 1 m3 prefabricated column production.

EquipmentTypeEnergy consumption parametersOperation time (h)Energy consumption (kJ)

Steel bar cutterGQ504 kw1.521.6
Steel bar benderGW507 kw125.2
Bridge craneLH5-16.5A4The fuel consumption per shift is 25.8 kg3412658.1
Steel bar hoop benderGF255 kw118
Forklift truckCPCD50-AG5586 kw0.5154.8