Predictive Analysis of Settlement Risk in Tunnel Construction: A Bow-Tie-Bayesian Network Approach

Table 9

Details of bow-tie components in Figure 9.

EventSymbolLogic link typeFailure model

Ground settlementExcessive surface settlementOR gate
Catastrophic geologyM1OR gate
Unforeseeable factorsM2OR gate
Excavation parametersM3AND gate
Confined waterX1Environmental failure
Ground cavity or flow sandX2Environmental failure
ObstaclesX3Environmental failure
Segment damageX4Operational error
Abnormal TBM shutdownX5Multiple failure
Seal failure at shield tailX6Multiple failure
Excessive deviation from axisX7Operational error
Equipment failureX8Multiple failure
Untimely groutingX9Facility failure
Excessive cutter head torqueX10Facility failure
Improper control of face pressureX11Facility failure
Excessive thrustX12Facility failure
Improper control of excavation speedX13Facility failure
TBM shutdownCE1Multiple failure
Grouting in settlement areaCE2Multiple failure
Bentonite injection to soil chamber and TBM shieldCE3Multiple failure