Research Article
Predictive Analysis of Settlement Risk in Tunnel Construction: A Bow-Tie-Bayesian Network Approach
Table 9
Details of bow-tie components in Figure
9.
| Event | Symbol | Logic link type | Failure model |
| Ground settlement | Excessive surface settlement | OR gate | — | Catastrophic geology | M1 | OR gate | — | Unforeseeable factors | M2 | OR gate | — | Excavation parameters | M3 | AND gate | — | Confined water | X1 | — | Environmental failure | Ground cavity or flow sand | X2 | — | Environmental failure | Obstacles | X3 | — | Environmental failure | Segment damage | X4 | — | Operational error | Abnormal TBM shutdown | X5 | — | Multiple failure | Seal failure at shield tail | X6 | — | Multiple failure | Excessive deviation from axis | X7 | — | Operational error | Equipment failure | X8 | — | Multiple failure | Untimely grouting | X9 | — | Facility failure | Excessive cutter head torque | X10 | — | Facility failure | Improper control of face pressure | X11 | — | Facility failure | Excessive thrust | X12 | — | Facility failure | Improper control of excavation speed | X13 | — | Facility failure | TBM shutdown | CE1 | — | Multiple failure | Grouting in settlement area | CE2 | — | Multiple failure | Bentonite injection to soil chamber and TBM shield | CE3 | — | Multiple failure |
|
|