Research Article
An Effective Approach to Input Variable Selection for Preliminary Cost Estimation of Construction Projects
Table 8
Selection order of input variables and distance to ideal input.
| Variable group (V1) | Symbol | Coefficient | BNP | Euclidean distance | Preferred order |
| Project size | V11 | 0.1525 | 0.2834 | 1.1099 | 1 | Project complexity | V13 | 0.1417 | 0.2586 | 1.1341 | 2 | Project scope | V14 | 0.1274 | 0.1853 | 1.1938 | 3 | Project type | V12 | 0.1499 | 0.1294 | 1.2168 | 4 | Project duration | V15 | 0.1253 | 0.1216 | 1.2396 | 5 | Project location | V16 | 0.1044 | 0.0995 | 1.2701 | 6 |
| Variable group (V2) | Number of bridges | V23 | 0.2436 | 0.4366 | 0.9432 | 1 | Existence of groundwater | V21 | 0.3191 | 0.3393 | 0.9488 | 2 | Bridge type | V22 | 0.2804 | 0.2801 | 1.0179 | 3 |
| Variable group (V3) | Inflation rate | V31 | 0.3409 | 0.1293 | 1.0921 | 1 | Site topography | V32 | 0.2657 | 0.1442 | 1.1276 | 2 | Soil type | V33 | 0.2195 | 0.0798 | 1.2066 | 3 |
|
|