Research Article

Numerical Study and Field Monitoring of the Ground Deformation Induced by Large Slurry Shield Tunnelling in Sandy Cobble Ground

Table 3

Settlements of different subsurfaces during excavation.

z = 0z = 2.0 mz = 6.4 mz = 10.6 mz = 12.8 mz = 14.4 m

Step 1
S1 (mm)−1.18−2.09−0.62−4.01−0.42−3.36−0.26−3.18−0.15−2.94−0.06−3.76
S1/S5 (%)6.8414.473.3426.331.9619.731.0917.340.5814.260.2215.47
ΔS1 (mm)−1.18−2.09−0.62−4.01−0.42−3.36−0.26−3.18−0.15−2.94−0.06−3.76
ΔS1/S5 (%)6.8414.473.3426.331.9619.731.0917.340.5814.260.2215.47
Step 2
S2 (mm)−2.82−5.80−2.90−5.59−3.03−4.84−3.21−5.81−3.42−6.80−3.68−7.55
S2/S5 (%)16.3540.1715.6036.7014.1328.4213.4331.6813.2332.9913.2131.07
ΔS2 (mm)−1.64−3.71−2.28−1.58−2.61−1.48−2.95−2.63−3.27−3.86−3.62−3.79
ΔS2/S5 (%)9.5125.6912.2610.3712.178.6912.3414.3412.6418.7312.9915.60
Step 3
S3 (mm)−8.73−10.93−9.49−10.82−11.24−12.27−12.97−16.30−14.40−17.67−15.80−18.99
S3/S5 (%)50.6175.6951.0571.0452.4372.0554.2788.8855.6885.7456.7178.15
ΔS3 (mm)−5.91−5.13−6.59−5.23−8.21−7.43−9.76−10.49−10.98−10.87−12.12−11.44
ΔS3/S5 (%)34.2635.5335.4534.3438.2943.6340.8457.2042.4652.7443.5047.08
Step 4
S4 (mm)−15.09−12.75−15.21−13.13−18.30−14.14−21.12−17.31−23.44−19.98−25.63−22.31
S4/S5 (%)87.4888.3081.8286.2185.3583.0388.3794.3890.6496.9492.0091.81
ΔS4 (mm)−6.36−1.82−5.72−2.31−7.06−1.87−8.15−1.01−9.04−2.31−9.83−3.32
ΔS4/S5 (%)36.8712.6030.7715.1732.9310.9834.105.5134.9611.2135.2813.66
Step 5
S5 (mm)−17.25−14.44−18.59−15.23−21.44−17.03−23.90−18.34−25.86−20.61−27.86−24.30
S5/S5 (%)100100100100100100100100100100100100
ΔS5 (mm)−2.16−1.69−3.38−2.1−3.14−2.89−2.78−1.03−2.42−0.63−2.23−1.99
ΔS5/S5 (%)12.5211.7018.1813.7914.6516.9711.635.629.363.068.008.19

is short for the numerical result; is short for the monitoring result.