Stage | Construction operation | Date |
|
1 | Preparation of Pit A, installation of 1st concrete strut | 2017/04/26–2017/05/22 |
Preparation of Pit B, installation of 1st concrete strut | 2018/12/01–2019/12/24 |
2 | Excavation of Pit A to 5.0 m, installation of 2nd steel strut | 2017/05/22–2017/06/18 |
Excavation of Pit B to 5.0 m, installation of 2nd steel strut | 2018/12/24–2019/01/05 |
3 | Excavation of Pit A to 8.0 m, installation of 3rd steel strut | 2017/06/18–2017/07/05 |
Excavation of Pit B to 8.0 m, installation of 3rd steel strut | 2019/01/05–2019/01/13 |
4 | Excavation of Pit A to 11.5 m, installation of 4th steel strut | 2017/07/08–2017/07/16 |
Excavation of Pit B to 11.5 m, installation of 4th steel strut | 2019/01/13–2019/01/18 |
5 | Excavation of Pit A to 15.0 m, installation of 5th concrete strut | 2017/07/16–2017/08/15 |
Excavation of Pit B to 15.0 m, installation of 5th concrete strut | 2019/01/18–2019/02/23 |
6 | Excavation of Pit A to 18.5 m, installation of 6th steel strut | 2017/07/26–2017/10/02 |
Excavation of Pit B to 18.5 m, installation of 6th steel strut | 2019/02/23–2019/03/11 |
7 | Excavation of Pit A to 21.5 m, installation of 7th steel strut | 2017/08/08–2017/10/15 |
Excavation of Pit B to 21.5 m, installation of 7th steel strut | 2019/03/11–2019/04/01 |
8 | Excavation of Pit A to 24.5 m, pouring of bottom slab | 2017/09/01–2017/10/30 |
Excavation of Pit B to 24.5 m, pouring of bottom slab | 2019/04/01–2019/04/20 |
|