Long-Term Deformation Analysis of Recycled Construction Waste Subgrade Filler
Table 5
Requirements of minimum CBR and maximum particle size for subgrade fillers.
| Position of filler application (below the top of roadbed) (m) | Minimum CBR (%) | Maximum particle (mm) | Expressway and first class highway | Second class highway | Third and fourth class highway |
| Fill subgrade | Upper roadbed (0–0.30) | 8 | 6 | 5 | 100 | Lower roadbed (0.30–0.80) | 5 | 4 | 3 | 100 | Upper embankment (0.80–1.50) | 4 | 3 | 3 | 150 | Lower embankment (>1.50) | 3 | 2 | 2 | 150 | Cut subgrade | 0–0.30 | 8 | 6 | 5 | 100 | 0.30–0.80 | 5 | 4 | 3 | 100 |
|
|