Implementation of Process-Based and Data-Driven Models for Early Prediction of Construction Time

Table 5

Target mean values for three different predictor values [63].

PredictorsTarget variable: ln(real time, days)

Purpose of the facilityTarget mean
43.45%Petrol station3.8491
54.31%Education6.6249
76.03%Bridge4.5354

ln(planned costs, euro)Target mean
10.86%9.053583.6889
10.86%9.350372.9957
10.86%9.442932.8332

ln(real costs, euro)Target mean
10.86%9.094593.6889
10.86%9.350372.9957
10.86%9.442932.8332

ln(planned time, days)Target mean
21.72%2.7080502.8519
21.72%2.9957322.8618
10.86%3.2188763.1355