Productivity comparison.

CategoryExisting processOptimized process

Days spent manufacturing (days)3224
Daily average manpower input (number of workers)9.3710.82
Daily average labor cost input (KRW)1,176,1801,009,511
Total manpower input (number of workers)299.81259.57
Total labor cost input (KRW)37,637,76832,304,364