Safety vibration limitation for tunnels and shafts in China.

Structure typeAllowable safety peak particle velocity (cm/s)
f ≤ 10 Hz10 Hz ≤ f ≤ 50 Hzf > 50 Hz

Hydraulic tunnels7∼839.03
Traffic tunnels10∼1237.02
Mining shafts15∼1831.51.5