Timber Portal Frames vs Timber Truss-Based Systems for Residential Buildings

Table 10

Man hour summary.

ā€‰Preerection/delivery labour (hours)Column (hours)Erection (hours)Total hours

Case A truss18.53.029.5051.00
Case A portal18.53.020.0041.50
Case B truss16.53.029.5049.00
Case B portal17.03.020.0040.00
Case C truss10.53.029.5043.00
Case C portal17.03.020.0040.00