Timber Portal Frames vs Timber Truss-Based Systems for Residential Buildings
Table 6
Summary of truss predelivery labour.
| ā | Case A | Case B | Case C |
| No. of trusses | 8 | 8 | 8 | Total cuts/truss | 17 | 15 | 9 | Total joints/truss | 6 | 6 | 6 | Total truss points | 68 | 60 | 36 | Column cuts | 12 | 12 | 12 | Column points | 6 | 6 | 6 | Total construction time (hours) | 18.5 | 16.5 | 10.5 | Total | $1,295.00 | $1,155.00 | $735.00 |
|
|