Research Article
Exact Overlap Rate Analysis and the Combination with 4D BIM of Time-Cost Tradeoff Problem in Project Scheduling
Table 2
The optimal overlapping strategy of the case.
| Overlap activity | Overlap rate | Overlap duration (days) | Rework duration (days) | Rework probability | Rework cost (dollars) |
| 1–5 | 0.218026 | 6.54 | 1.31 | 0.10 | 256.69 | 1–6 | 0.299989 | 7.20 | 1.44 | 0.46 | 388.77 | 5–7 | 0.21767 | 3.92 | 0.78 | 0.10 | 153.51 | 6–8 | 0.499969 | 12.00 | 2.40 | 0.41 | 1079.86 | 6–9 | 0.599973 | 15.00 | 3.00 | 0.45 | 1619.86 | 2–10 | 0.799835 | 26.39 | 5.28 | 0.52 | 3800.03 | 6–10 | 0.799959 | 26.40 | 5.28 | 0.52 | 3801.21 | 7–11 | 0.599985 | 12.00 | 2.40 | 0.58 | 1295.93 | 8–11 | 0.599974 | 12.00 | 2.40 | 0.58 | 1295.89 | 5–12 | 0.285024 | 8.55 | 1.71 | 0.10 | 438.69 | 9–12 | 0.286209 | 8.59 | 1.72 | 0.10 | 442.35 | 10–12 | 0.285853 | 8.58 | 1.72 | 0.10 | 441.24 | 3–13 | 0.499996 | 12.00 | 2.40 | 0.55 | 1079.98 | 4–14 | 0.749908 | 13.50 | 2.70 | 0.50 | 1822.06 | 9–14 | 0.749951 | 13.50 | 2.70 | 0.50 | 1822.26 | 12–15 | 0.8 | 12.8 | 2.56 | 0.64 | 1843.2 | 13–16 | 0.217192 | 6.52 | 1.30 | 0.10 | 254.73 | 14–16 | 0.218397 | 6.55 | 1.31 | 0.10 | 257.57 | 11–17 | 0.699977 | 16.80 | 3.36 | 0.48 | 2116.66 | 14–17 | 0.699992 | 16.80 | 3.36 | 0.48 | 2116.75 | 15–17 | 0.699999 | 16.80 | 3.36 | 0.48 | 2116.80 | 16–18 | 0.216634 | 3.90 | 0.80 | 0.10 | 152.05 | 17–18 | 0.218784 | 3.94 | 0.79 | 0.10 | 155.09 |
|
|