Exact Overlap Rate Analysis and the Combination with 4D BIM of Time-Cost Tradeoff Problem in Project Scheduling

Table 2

The optimal overlapping strategy of the case.

Overlap activityOverlap rateOverlap duration (days)Rework duration (days)Rework probabilityRework cost (dollars)

1–50.2180266.541.310.10256.69
1–60.2999897.201.440.46388.77
5–70.217673.920.780.10153.51
6–80.49996912.002.400.411079.86
6–90.59997315.003.000.451619.86
2–100.79983526.395.280.523800.03
6–100.79995926.405.280.523801.21
7–110.59998512.002.400.581295.93
8–110.59997412.002.400.581295.89
5–120.2850248.551.710.10438.69
9–120.2862098.591.720.10442.35
10–120.2858538.581.720.10441.24
3–130.49999612.002.400.551079.98
4–140.74990813.502.700.501822.06
9–140.74995113.502.700.501822.26
12–150.812.82.560.641843.2
13–160.2171926.521.300.10254.73
14–160.2183976.551.310.10257.57
11–170.69997716.803.360.482116.66
14–170.69999216.803.360.482116.75
15–170.69999916.803.360.482116.80
16–180.2166343.900.800.10152.05
17–180.2187843.940.790.10155.09

We are committed to sharing findings related to COVID-19 as quickly and safely as possible. Any author submitting a COVID-19 paper should notify us at help@hindawi.com to ensure their research is fast-tracked and made available on a preprint server as soon as possible. We will be providing unlimited waivers of publication charges for accepted articles related to COVID-19. Sign up here as a reviewer to help fast-track new submissions.