The top ten risk variables.

Name of risk factorCode of risk factorRisk factorCloseness indexRank

Unskilled labour [9]E2Labour0.8481
Electricity problemG3Operational0.8372
Undisciplined labour [9]E3Labour0.8023
Lack of labour [9]E1Labour0.7594
Self-protect instruments of a construction workerH3Health and safety of work0.7515
Low productivity of labour [9]E4Labour0.7476
Fuel scarcity [9]B9Equipment0.6957
Broken equipment [9]B5Equipment0.6918
Less experience of the contractorF3Contractor managerial0.6909
The delay in material delivery [9]A2Material0.67610