Research Article
Implementing Fuzzy TOPSIS on Project Risk Variable Ranking
Table 3
The top ten risk variables.
| Name of risk factor | Code of risk factor | Risk factor | Closeness index | Rank |
| Unskilled labour [9] | E2 | Labour | 0.848 | 1 | Electricity problem | G3 | Operational | 0.837 | 2 | Undisciplined labour [9] | E3 | Labour | 0.802 | 3 | Lack of labour [9] | E1 | Labour | 0.759 | 4 | Self-protect instruments of a construction worker | H3 | Health and safety of work | 0.751 | 5 | Low productivity of labour [9] | E4 | Labour | 0.747 | 6 | Fuel scarcity [9] | B9 | Equipment | 0.695 | 7 | Broken equipment [9] | B5 | Equipment | 0.691 | 8 | Less experience of the contractor | F3 | Contractor managerial | 0.690 | 9 | The delay in material delivery [9] | A2 | Material | 0.676 | 10 |
|
|