Empirical Study on the Obstacles to the Success of Joint Ventures in Construction Projects

Table 5

Results of statistical analysis.

Variables (potential obstacles of CJV success)Senior management group (group 1)Project management group (group 2)Technical/site group (group 3)All respondent groupResult of ANOVA
Mean valueRankMean valueRankMean valueRankMean valueRankFSig.

V83.9223.9813.6813.9111.5600.215
V73.9223.8623.5923.7921.1570.319
V93.6763.8333.5143.7131.3540.263
V43.7543.7453.5923.6940.3730.690
V33.5883.8143.4383.6552.2870.107
V53.7543.7263.4953.6460.9370.395
V64.0013.6073.4193.5871.9630.146
V23.42123.5293.4663.4980.0930.911
V133.6763.5783.24133.4791.4430.241
V103.50113.48113.38113.45100.1660.847
V163.42123.43133.4663.44110.0120.988
V123.25153.48113.4193.43120.3400.713
V143.17173.5293.30123.40130.9710.382
V173.5883.33143.24133.33140.5650.570
V113.42123.26153.19153.25150.2690.765
V13.25153.26153.14163.21160.3150.731
V153.5883.22172.95173.19172.4970.086
Number of survey responses125938109
Kendall’s coefficient of concordance (W)0.1460.0740.0670.065
Actual calculated chi-square value28.04368.98539.831111.595
Critical chi-square value from the table26.3026.3026.3026.30
Asymptotic level of significance0.0310.0000.0010.000