Surface Settlement Damage Model of Pile-Anchor Supporting Structure in Deep Excavation

Table 2

Division of monitoring stages.

Monitoring stageConstruction conditionsMonitoring dateSettlement curve

1Excavating to −3 m, constructing anchor at −2 m6.29–7.22Figure 10(a)
2Excavating to −5.5 m, constructing anchor at −4.5 m7.23–8.15Figure 10(b)
3Excavating to −8.5 m, constructing anchor at −7.5 m8.16–9.18Figure 10(c)
4Excavating to −11 m, followed by constructing foundation9.19–11.10Figure 10(d)
5Constructing building floor11.11–12.08Figure 10(e)