Experimental Study on Influence of Connection Defects on Joint Strength of Half-Grouted Sleeve Splicing of Rebar

Table 3

Experimental conditions.

TypeSpecimen’s numberExperimental condition

AGTZB16-DZ-BM-1/2/3The control group of rebar alignment and full grout
BGTZB16-DZ-WM-100 mm-1/2/3Vertical insufficient grouting height specimen (vertical grouting height is 100 mm)
CGTZB16-DZ-WM-20%-1/2/3Insufficient compactness specimen (20% of porosity)
DGTZB16-PZ-BM-1/2/3Rebar offset joint specimen (rebar eccentricity of 5 mm contacts the sleeve wall)
EGTZB16-DZ-120/104/88 mm-BM-1/2/3Insufficient anchoring length specimen (the rebar insertion depths were 120 mm, 104 mm, and 88 mm)
FGTZB16-DZ-BM-30 min-1/2/3Grouting specimen after 30 min delay