Abstract

In order to deeply understand the appropriate embedded depth of the foundation pit diaphragm wall in granite residual soil area, a physical model of the diaphragm wall with inner support for foundation excavation was constructed according to the actual project in the proportion of 1 : 30. The distribution of Earth pressure, the horizontal displacement of the wall, and the settlement behind the wall were obtained by physical experiments. The numerical simulation was then performed to authenticate the results from physical modeling. It was observed that the embedded depth of the diaphragm wall had the most obvious influence on the horizontal displacement of the wall. Moreover, the final soil settlement and its influence were significantly increased with the decrease in embedded depth. The analysis results also suggested that the control value for the embedded depth of the wall should not be less than 0.36 H (H is the excavation depth of the foundation pit).

1. Introduction

More excavation support problems related to underground space engineering are highlighted with the increasing contradiction between the rapid development of cities and the lack of land resources in China. The granite residual soil is widely distributed in the south of China, and the diaphragm wall has been used in this area due to its high efficiency and safety under the condition that the foundation pit is developing superlarge and ultradeep. The diaphragm wall plays a critical role in the support structure which accounts for 70%–80% of the total support structure costs [1]. Therefore, appropriate control of the embedded depth of the diaphragm wall is of great significance for engineering construction.

In the past 40 years, predecessors carried out further studies about the foundation pit in the granite residual soil area. The development of foundation pit support technology in Shenzhen can be divided into four stages: unconscious application, initial application of various technologies, soil-nail wall era, and rational application of various technologies [2]. After approximately 40 years of development, the foundation pit project in Shenzhen has moved toward the fifth stage, which focuses on deformation control [3]. Nowadays, the diaphragm wall has been widely used in Shenzhen as a kind of excavation engineering technology due to its safety, quality, impermeability, and minimized environmental impact [4, 5]. Wang and Liu [6] collected the deformation data of 13 granite residual soil foundation pits in the south of China, combined with the existing statistical results of foundation pit deformation in other areas of China, and made a comparative analysis of the deformation characteristics of deep foundation pits in this area. Bai et al. [7] took a foundation pit in Guangzhou as an example to study the effect of embedded depth on the deformation of the diaphragm wall and found that the horizontal displacement of the diaphragm wall gradually decreases as the embedded depth increases. At present, it can be widely recognized that if the embedded depth is shallower, the horizontal displacement of the diaphragm wall is too large, and the foundation pit can be easily destabilized; if the embedded depth is very large, it is very likely to construct the embedded section into the rock stratum with low weathering, which will cause great difficulties for the construction, and the engineering cost will significantly increase. At this time, the effect of increasing the embedded depth on deformation control of the foundation pit is not obvious.

In order to deeply understand the influence of the diaphragm wall embedded depth of the foundation pit in the granite residual soil area, this study made a physical test model according to a similar theory with two similar soil materials: granite residual soil and fully weathered granite. The whole process of the deep foundation pit excavation with the inner support system was simulated, and numerical simulation was used to compare the changes in the physical model experiment.

2. Scale Similarity and Physical Model

2.1. Scale Similarity

The main requirements for the similarity of the physical model experiment are as follows: the boundary conditions of the model, geometry, density, strength, and stress changes of similar materials should follow certain similar laws. The ratio of physical quantities with the same dimensions between the prototype and the model is called a similar scale and is represented by C. The geometric similarity coefficient generally determines first when conducting a similar model experiment. The geometric similarity coefficient is Ci = n, and the density similarity coefficient is Cy = 1. According to the dimensional analysis method, it should be known that the physical quantities of the same dimension are similar to scale C as follows:where is the similarity scale of density, is the similarity scale of internal friction angle, is the similar scale of Poisson’s ratio, is the similarity scale of strain, is the similarity scale of cohesion, is the similarity scale of elastic modulus, and is the similar scale of stress.

2.2. Engineering Prototype
2.2.1. Project Overview

The proposed site is located at No.1, Tairan 7th Road, Chigongmiao Industrial Zone, Futian District, Shenzhen City. It is adjacent to Tairan 8th Road on the north side and Binhe Avenue on the south side. Shenzhen Metro Line 9 passes near the site and the nearest station is about 41 m from the study site. The west side is Tairan 9th Road, and the east side is another construction project. The overall terrain of the proposed site is relatively flat, with a construction land area of 5,775.05 m2. The site is planned for the business center, with 4 basement floors. The foundation pit site and research scope are shown in Figures 1 and 2, respectively.

According to the current drilling, the stratum in the site from top to bottom is as follows: the newly deposited artificial filling soil (Q4ml), the new commission sea-land interaction sediments (Q4mc), the diluvium layer (Q3al + pl), the Quaternary eluvium (Qel), and the underlying bedrock of early Cretaceous coarse-grained granitic of the Yanshanian (). The composition of the site foundation soil is shown in Table 1.

3. Design of Support Structure

The excavation depth of the foundation pit is 19.3 m, the plane figure is approximately rectangular, the length is 77.9 m, and the width on both sides are 63.5 m and 75.4 m, respectively. The diaphragm wall is 1 m in width and 28.3 m in length with the impermeability grade of S8. A reinforced concrete crown beam is set on the top of the wall with section size b × h = 1 m × 1 m. Three reinforced concrete inner supports are set in the middle with the cross-sectional size of b × h = 1 m × 1 m, and the distances between the supports from top to bottom are 7.3 m, 5.1 m, and 6.4 m, respectively. The vertical support is a steel pipe column, the upper half of which is 600 mm in diameter and 16.9 m in length and the lower half is 1000 mm in diameter and 15.6 m in length. The concrete grade of the diaphragm wall, crown beam, and waist beam is C 30, the concrete strength grade of the cushion is C 15, and the strength grade of column steel is Q 235. The thickness of the reinforced protective layer of the diaphragm wall is 50 mm. The thickness of the reinforced protective layer in inner support is 35 mm. The profile of the foundation pit is shown in Figure 3.

3.1. Physical Model

The foundation pit support scheme is composed of a diaphragm wall with an inner support structure. During the physical modeling experiments, considering the symmetrical shape of the foundation pit and the supporting structure in the foundation pit, a quarter of the foundation pit is assessed by the physical simulation experiment. The area under study for this experiment is shown in Figure 2.

4. Test Methods

4.1. Test Scheme

Previous research shows that the influence of dry density and moisture content of the material on its properties was rarely considered when preparing similar materials [810]. Therefore, on the basis of previous research findings, this study has taken quartz sand and bentonite as raw materials, weight ratio of sand and bentonite, dry density, and moisture content as three influencing factors, set up 4 levels, and designed a total of 16 groups of orthogonal tests to conduct the preparation research of similar materials. According to the orthogonal test results, a large number of tests were carried out under the conditions of changing parameters, and finally, two similar materials of simulated granite residual soil and fully weathered granite used in the physical experiments were obtained. In addition, the soil layer above the gravelly clayey soil was simulated by fully weathered granite residual soil. The particle size range of quartz sand was 1 mm to 2 mm. The deformation modulus E0 is as follows:

The Earth pressure during the experiment would not exceed 50 kPa. The values of p2 and p1 were 25 kPa and 50 kPa, respectively, the variable modulus of Earth pressure within 50 kPa was obtained, which was more in line with the experimental situation. The proportions of similar materials used in the study are shown in Table 2. The physical-mechanical parameters of the prototype and model material are shown in Table 3.

According to the scale of the foundation pit and taking the excavation depth H as the reference, the length, height, and width of the model were taken as 4 H, 2 H, and 2 H, and the similarity coefficient as n = 30. The size of the model box was determined as 2.5 m in length, 1.5 m in width, and 1.5 m in height (Figure 4). The diaphragm wall was simulated by the PPR board in the physical model. According to the similarity ratio, the thickness of the board was 33 mm and the length was 98 cm. The inner support and waist beam were simulated by 33 mm and 40 mm thick steel, respectively, and the anchorage to the diaphragm wall was fixed by self-drilling nails. The column was simulated by iron rods with diameters of 3 cm and 2 cm and connected with the inner support by iron wire tying.

4.2. Data Collection

During the experiment, a joint monitoring method of stress and displacement was adopted. The stress monitoring was used for the Earth pressure cell to test the Earth pressure of the diaphragm wall under all working stages. The equipment was a 20-channel 100 Hz dynamic-static strain apparatus and the Earth pressure cell. Displacement monitoring was mainly performed to monitor the displacement of the diaphragm wall and vertical deformation of the surrounding soil in real time. The equipment adopts a dial indicator and three-dimensional (3D) deformation monitor (Figure 4). The length of the 3D deformation monitor was kept as 100 cm, in which the displacement of one point can be monitored after every 25 cm. In this experiment, two 3D deformation monitors were installed staggered on the diaphragm wall. The diaphragm wall was 98 cm long, so that the displacement of the wall was monitored after every 12.5 cm and the displacement data of 8 points were monitored at the same time. The above sensors were arranged in the center of the diaphragm wall. In Figure 5, “A” represents the position sensor, “B” represents the monitoring point of the Earth pressure cell, and “H” represents the length of the diaphragm wall. The layout of each sensor is shown in Figure 6.

4.3. Experimental Procedure
4.3.1. Model Installation

The first step in the experimental procedure was to install the displacement sensors and Earth pressure cell. One Earth pressure cell was arranged on the lower side of each row of waist beams, and three Earth pressure cells were densely arranged in the embedded section of the diaphragm wall. The second step was to embed the diaphragm wall and the columns. The third step was to install the dial indicator on the surface of the soil behind the diaphragm wall after the soil compaction was completed, which was used to determine the vertical deformation of the soil settlement during the excavation of the foundation pit.

4.3.2. Physical Experiment Stages

The excavation process of the foundation pit was completely in accordance with the actual foundation pit excavation.Stage 1: the excavation face was taken as zero-point, excavated 4 cm, and installed within the first row of inner support at the top of the diaphragm wallStage 2: excavated 24.3 cm on the basis of stage 1, excavated to 28 cm, and installed the second row of inner supportStage 3: excavated 17 cm on the basis of stage 2, excavated to 45 cm, and installed the third row of inner supportsStage 4: excavated 21.3 cm on the basis of stage 3, and excavated to 64 cm as shown in Figure 7

In the aforementioned excavation physical process, the soil settlement, Earth pressure and diaphragm displacement were recorded in real time. So far, the whole process of the physical excavation experiments for the embedded length of a diaphragm wall was completed. The embedded length was then changed and repeated the above steps under the stages of L/H = 0.36 (24 cm) and L/H = 0.3 (19 cm) to obtain the distribution laws of displacement and Earth pressure under different diaphragm wall embedded depths.

5. Numerical Simulation

5.1. Model Parameter Selection

The study took a quarter of the foundation pit for 3D modeling calculation analysis same as the physical model experiment. Considering the influence of wall displacement and ding to the analysis results of horizontal displacement and settlement, the settlement, the height of the modeled foundation pit was taken as the influence range of the surrounding soil at twice the excavation depth (H = 19.3 m). The overall size was 78.8 m (length) × 72.8 m (width) × 40 m (height), as shown in Figure 8.

The modified Coulomb constitutive model was adopted for soil mass. The traditional Mohr–Coulomb model was an elastoplastic model, which could not consider the influence of soil unloading modulus changes. The final simulated value had a great difference from the actual monitoring data. The modified Mohr–Coulomb constitutive model could be regarded as an improved version of the former. The latter had the same shear yield surface as the former, but it used rounded corners to make the model more convergent. The compression yield surface was elliptical, and its shear yield surface and compression yield surface did not affect each other. The model could consider the change of elastic modulus of soil with the change of stress, so it was more practical than the Mohr–Coulomb model. The soil parameters of the model and the supporting structure parameters are shown in Table 4 and 5, respectively.

According to the excavation and support process of the foundation pit, the simulation calculation process was divided into the following 4 stages: Preparation stage: it consists of the generation of the initial stress field, activation of all soil layers, activation of deadweight and boundary displacement constraint conditions, reset of the displacement, and the derivation of diaphragm wall and columnStage 1: the excavation surface was taken as the starting point, excavated 1 m, and overexcavated 0.5 mStage 2: the first layer was set as the inner support and waist beam at the site of −0.5 m, excavated 7.3 m on the basis of stage 1, and overexcavated 0.5 mStage 3: the second layer was set as the inner support and waist beam, excavated 5.1 m on the basis of stage 2, and overexcavated 0.5 mStage 4: the third layer was set as the inner support and waist beam and excavated 5.9 m on the basis of stage 3

6. Results and Discussion

6.1. Comparison between the Physical Modeling and Numerical Simulations

The results of the physical experiments were expanded 30 times in proportion, and compared with the results of the numerical simulation, the comparison diagram of wall displacement, soil settlement, and Earth pressure were obtained successively. Among them, M−1 represented the physical experiment stage 1, N−2 represented the numerical simulation stage 2, and so on.

The trends of numerical simulation and physical experiments are basically the same as depicted in Figure 9. In stage 1, stage 2, and stage 3, the inner supports were installed after excavation, and the wall displacement did not significantly change. Stage 4 had a large excavation depth and no new inner support was installed, resulting in the largest change in the wall displacement. The maximum deformation values of the wall were very close to 11.3 mm and 15.9 mm. The minimum displacement of the wall appeared below the excavation surface of the foundation pit, indicating that the soil had a restraint effect on the wall and the embedded effect was obvious at the excavation surface. Both the physical experiments and the numerical simulation of the wall displacement curve were “big belly-shaped,” and the maximum horizontal displacement position dhm was located at the ratios of 0.33 H and 0.57 H, respectively. The average value of the maximum horizontal displacement position of the granite residual soil foundation pit in Shenzhen is 0.56 H [6], which was very close to the experimental results.

The physical experiments and numerical simulation of the soil settlement are shown in Figure 10, both of which are “groove-shaped,” with the maximum settlement values of 7.7 mm and 6.6 mm, respectively, and the maximum values appeared at 0.15 H and 0.40 H from the pit edge. From the abscissa at 22 m in Figure 10, it could be found that the settlement value of the numerical simulation was larger at the edge of the pit. This was caused by a certain time effect in the physical experiment process, but it did not affect the deformation law of the settlement curve.

It can be seen from Figures 11 and 12 that the Earth pressure of the physical experiments is greater than the numerical simulation. As the physical experiment soil sample was reshaped, it caused undergoing a series of steps as drying, stirring, and compaction during the experiments. Then, the structure of the undisturbed soil had been lost, resulting in a certain difference between the results of physical experiments and numerical simulations. In general, it can be seen from Figures 912 that the results and changing trends of the physical model experiments and the numerical simulation are basically the same, which can represent the accuracy of the physical model experiments.

6.2. Comparison between Physical Experiment and Monitoring Results

A comprehensive dynamic monitoring of the foundation pit supporting structure and the surrounding environment was carried out during the construction of the foundation pit, including the lateral displacement (XC) of the diaphragm wall and the soil settlement (W) behind the wall as shown in Figure 2. The layout of the measuring points is also shown in Figure 2. The results of the physical experiments were enlarged by 30 times and compared with the monitoring results. The results of the settlement and displacement are very close as shown in Figure 13. The two monitoring points of XC1 and W2 were 10.2 mm and 7.4 mm, and the difference from the physical experiment result was 2.3 mm and 1.6 mm, respectively (accounting for 22.5% and 21.6% of the actual measured value, respectively). The difference between the monitoring and the experiment results is not very large, which shows the accuracy of the physical model experiment.

6.3. Minimum Embedded Depth

The wall displacement, soil settlement, and Earth pressure were obtained through the excavation physical experiments of foundation pit with different embedded depths of diaphragm walls (L/H = 0.36, L/H = 0.3).

6.3.1. Wall Horizontal Displacement

It can be seen in Figures 14 and 15 that the lateral displacement of the diaphragm wall is as “large belly”. The horizontal displacement of the diaphragm wall increases continuously with the increase of excavation depth; especially after stage 4, the increase of displacement is particularly obvious. The smaller the embedded depth is, the greater the final horizontal displacement of the wall with the change in embedded depth is. The maximum wall displacement value reaches 0.14% H, which is very close to the average value of the maximum horizontal displacement of the foundation pit wall in the granite residual soil area, as 0.13% H [6]. It was found from experiments that the displacement at the top of the wall is generally small, which shows that the crown beam plays a significant role.

6.3.2. Soil Settlement Behind the Walls

It can be seen in Figures 16 and 17 that with the increase in distance from the diaphragm wall, the soil settlement will first increase and then decrease significantly, forming a groove-shape. The maximum soil settlement appears at about 0.23 H from the pit. The maximum soil settlement gradually increases with the continuous decrease in embedded depth, and the maximum settlement value under the two embedded depths was 0.25 mm, δvm/H = 0.04%, and 0.45 mm, δvm/H = 0.07%, respectively. The influence range of the settlement was also expanded significantly with the decrease in embedded depth, and hence the influence range of the last settlement exceeded the monitoring range of 70 cm.

6.3.3. Earth Pressure

The interior of the foundation pit belongs to the passive Earth pressure area, while the exterior of the foundation pit belongs to the active Earth pressure area according to the displacement law of the diaphragm wall. The Earth pressure in front of the wall decreased continuously with the increasing depth of excavation. The excavation depth is shallow, so the Earth pressure does not change significantly during the first stage; when the excavation depth was deepened, the Earth pressure significantly changed. The deformation of the wall to the interior of the foundation pit gradually increased with the increase in excavation depth, resulting in a decrease in the Earth pressure behind the wall (Figures 1821).

7. Conclusions

(1)The lateral displacement of the wall during the whole process of foundation pit excavation shows the “big belly” shape: the middle part of the wall has the largest displacement, while the lower and upper parts have small displacement. The horizontal displacement of the wall increased, and the position of the maximum displacement value moves down with the increase of the excavation depth. By decreasing the embedded depth, the greater final horizontal displacement of the wall occurred with the maximum value of 0.9 mm, 0.14 H%.(2)The soil settlement behind the diaphragm wall was gradually increased with the progress of the excavation. The maximum settlement position appears approximately 0.23 H, with a maximum value of 0.45 mm, δvm/H = 0.07%. The final settlement increased significantly with the decrease in embedded depth, and the influence range of settlement also increased significantly, but it did not change the groove-shaped rule of soil settlement.(3)The passive Earth pressure in front of the wall increases linearly with the depth. The passive Earth pressure in the bottom soil of the pit decreases with the increase of the excavation depth. The excavation depth of stage 1 is relatively shallow, and the decrease of the Earth pressure is not obvious. The Earth pressure decreased obviously with the increase in excavation depth under the latest stages, because the displacement of the wall was very small during the experiment, the Earth pressure in front of and behind the wall is distributed in a triangle, which was more in line with the distribution law of the static Earth pressure.(4)According to the analysis results of horizontal displacement and settlement, the wall displacement reached the critical value of 30 mm in the “Technical Code for retaining and protection of excavation in Shenzhen city” at the embedded depth of 0.36 H [14]. Therefore, it is recommended that the embedded depth should not be less than 24 cm (0.36 H) for the diaphragm wall with inner supports structure.

Data Availability

The data used to support the findings of this study are included within the article.

Conflicts of Interest

The authors declare that they have no conflicts of interest.

Acknowledgments

This research was funded by the National Natural Science Foundation of China (nos. 41572257 and 41972267).