Replacement of Cable Stays in Yonghe Bridge in Tianjin, China

Table 2

Final cable adjustment scheme in Yonghe Bridge.

Construction sequenceStay numberCable force increment (kN)Construction sequenceStay numberCable force increment (kN)

Step 1SC9′482Step 8SC11343
NC9′677NC11347
Step 2SC10′605Step 9SC7240
NC10′836SC4′259
Step 3SC11′601Step 10SC8′202
NC11′617SC8266
Step 4SC8′735NC8151
SC8652NC8′186
NC8450Step 11SC7′140
NC8′681SC9229
Step 5SC6′700NC6120
SC6748NC7′120
NC6548Step 12SC6′150
NC6′640SC6150
Step 6SC7′595NC6′150
NC7′658Step 13NC4′184
Step 7SC5′400SC1291
SC5206Step 14SC2−137
NC5200
NC5′192

Note. A positive value shows an stressing increment, while a negative value shows a loosening increment.