Research Article

Research on Lean Planning and Optimization for Precast Component Production Based on Discrete Event Simulation

Table 4

Instantaneous utilization of each resource after 1500 simulations.

CodeNameInstantaneous utilization of resource
AverageMinimum averageMaximum average

1Cleaning workstation0.30570.29260.3186
2Steel installation workstation0.10340.09690.1092
3Checking workstation before concrete pouring0.15330.14400.1634
4Concrete pouring and vibrating workstation0.15290.14440.1621
5Resting workstation0.13940.12920.1503
6Stacking crane0.18610.16950.2051
7Curing kiln0.30530.29830.3120
8Mold releasing workstation0.07230.06860.0755
9Buffer area for end face cleaning0.12400.12120.1267
10Temporary stacking area0.12400.12120.1267