Risk Assessment of Deep Foundation Pit Construction Based on Analytic Hierarchy Process and Fuzzy Mathematics

Table 2

Indexes of the consequence severity.

AssignmentSevere injury (F) death (SI)/personEconomic losses/10,000 RMBConstruction delays/monthsEnvironmental impactsSocial impacts

5SI > 10>1000>9Very largeTerrible
49 ≥ SI ≥ 3 or F ≥ 10(1000, 500](9, 6]BigSerious
32 ≥ SI ≥ 1 or 9 ≥ F ≥ 2(500, 100](6, 3]BigMore serious
2F = 1 or 10 ≥ minor injuries ≥ 2(100, 50](3, 1]SmallerNeed to consider
1Minor injuries = 1<50<1Very smallIgnorable