Risk Assessment System Based on Fuzzy Composite Evaluation and a Backpropagation Neural Network for a Shield Tunnel Crossing under a River

Table 9

Assessment results.

ItemFuzzy composite evaluationRisk evaluation by BPNN

Single risk itemVault settlement, ground settlement, and leakageVault settlement, ground settlement, and leakage
Combined risk itemsLandslides and water seepageLandslides and water seepage
Risk-indicator valueRA = 78%; RB = 73%RA = 81%; RB = 73%
Risk levelHigh riskHigh risk
CountermeasuresAdjust the spacing of tunnel excavation for double lines to reduce disturbance; improve the intensity level of synchronous slurry; carry out double-liquid grouting after synchronous grouting; increase grouting pressure and soil bin pressure appropriately to control sedimentation; reduce digging speed; carry out stratum reinforcement; monitor in real time and adjust grouting parameters in time