Proposition of a Model for Selection of the Hybrid Contract Implementation Strategy for a Pilot Project of Regular Road Maintenance in Montenegro

Table 3

Overview of selected works for implementation of the model.

No.Description of the itemMeasurement unitsValue of paid works per road section for period 2015–2019 (€)Contribution in total value (%)
S1S2S3S4S5

1Hot patch asphalt (repair of larger surfaces)m21, 101, 509892, 105858, 927729, 203591, 94922.17
2Protection of slopes with suspended steel wire meshesm2696, 213483, 358633, 173314, 801601, 18614.49
3Marking horizontal signalization lineskm536, 609495, 607312, 100314, 797401, 49710.94
4Installation and replacement of safety fencem199, 129271, 258303, 084182, 555229, 0046.29
5Hot patch asphalt (repair smaller surfaces and potholes)t12, 828235, 571322, 500206, 951128, 2834.81
6Inspection serviceh215, 461183, 298122, 467140, 096238, 9604.78
7Cleaning gutterm151, 941128, 779110, 145207, 225188, 8784.18
8Cleaning of landslide materialm3134, 357146, 02319, 813228, 236242, 0954.09
9Cutting shrubs, trees, and grassm256, 897143, 633112, 991136, 544148, 6513.18
10Laying of the levelling wearing course AB 11t147, 700165, 84597, 22156, 319119, 4103.11
11Forging slopes from unstable parts of rocksm353, 098220, 28114, 88565, 372117, 3482.50
12Repair of stone wallsm32,24129,997352,254010,7552.10
13Cleaning of drainage channels and ditchesM22,03779,48791,20598,38642,0861.77
14Mechanical scraping-profiling of existing asphalt pavementm288,96383,27250,09341,07444,7961.64
Total86.06