Proposition of a Model for Selection of the Hybrid Contract Implementation Strategy for a Pilot Project of Regular Road Maintenance in Montenegro

Table 7

Overview of optimal strategies using the Laplace criterion (pi = 1/3) for selected works.

No.Work itemUnit measureLaplace criterion for pj = 1/3Optimal strategyRecommendation for Serbian conditions

1Hot patch asphalt (repair of larger surfaces)m268272.4LSBoQ
2Protection of slopes with suspended steel wire meshesm233105.0LSBoQ
3Marking horizontal signalization lineskm111.6BoQBoQ
4Installation and replacement of safety fencem11689.3BoQBoQ
5Hot patch asphalt (repair smaller surfaces and potholes)t142.8BoQBoQ
6Inspection serviceh16.1BoQLS
7Cleaning gutterm14068.4LSLS
8Cleaning of landslide materialm385.8BoQBoQ
9Cutting shrubs, trees, and grassm282635.8LSLS
10Laying of the levelling wearing course AB 11t919.1LSBoQ
11Forging slopes from unstable parts of rocksm35636.0LSLS
12Repair of stone wallsm33939.4LSBoQ
13Cleaning of drainage channels and ditchesm1107183.2LSLS
14Mechanical scraping-profiling of existing asphalt pavementm219028.7LSBoQ