Determination of the Installation Time of Secondary Liner during Excavation of Large Cross-Section Double-Arch Tunnels

Table 5

Safety factor of controlling points of initial support of different plans.

PlanInternal forceControlling points

Plan 1N−746.6−652.0−599.3−475.1−662.0−792.0
M−8.0−128.7−45.4−107.6−160.837.0
K3.21.32.71.51.02.4
Plan 2N−802.1−588.3−573.4−420.4−595.1−840.5
M−10.4−137.1−52.5−122.7−176.840.1
K2.91.22.51.30.92.3
Plan 3N−644.4−604.7−542.1−431.1−580.1−698.8
M−6.2−110.2−37.0−87.8−132.130.5
K3.71.53.11.91.22.8
Plan 4N−700.7−541.2−514.0−374.9−512.7−749.0
M−8.3−118.6−44.3−103.0−148.533.8
K3.31.42.91.61.12.6

N : axial force, kN; M : bending moment, kN·m; and K : safety factor.