Study on Deformation Law of Deep Foundation Pit with the Top-Down Method and Its Influence on Adjacent Subway Tunnel

Table 1

Main construction stages.

StageConstruction operationScheduled start date

1Construction of the diaphragm wall of section C11/01/2013
2Construction of the ACIP piles of section C, excavation, and construction of sections A and B02/01/2014
3Excavation to a depth of 2.3 m and casting of slab B010/20/2014
4Excavation to a depth of 7.3 m and casting of slab B101/17/2015
5Excavation to a depth of 10.8 m and casting of slab B202/04/2015
6Excavation to a depth of 14.3 m and casting of slab B305/27/2015
7Excavation to a depth of 18.5 m and casting of the basement slab07/21/2015